Brisbane’s new runway is almost ready to take off

Brisbane new runway

The application of the final layer of asphalt for Brisbane’s new runway is underway, marking a significant milestone for the project.

Over the next three months, more than 100,000 tonnes of aircraft-grade asphalt will be placed on top of the runway’s 2.5ms of compacted sand and 600mm-layer of fine crushed rock.

Fulton Hogan has been subcontracted by Skyway to produce a specially-designed asphalt on site that allows flexibility, load-spreading capacity, deformation resistance and the ability to withstand aircraft-induced shear stresses and high temperatures.

Paul Coughlan, Project Director, says Brisbane’s new runway is the biggest and most satisfying project he has ever been involved in.

“After nearly 15 years as Project Director, I am just as passionate now as I was when I started thanks to moments like this.

“Asphalt is the final layer of Brisbane’s new runway – the icing on the cake that is an internationally tried and tested runway pavement design.

“Given that site preparation and reclamation works for the new runway commenced way back in July 2012, it is incredibly exciting to be reaching a point where the end of construction is now in sight,” Mr Coughlan said.

Skyway Joint Venture Project Director, Graeme Fenemore, said the milestone is representative of the significant progress made to date which has been the culmination of an open and collaborative relationship between Skyway and BAC.

“Together we have implemented innovative engineering solutions while always putting the safety of our workforce first, proudly recording in excess of 2.2 million hours with an outstanding safety record.

“By continuing the momentum we have, I am confident the project will be delivered safely to the satisfaction of the wider community.”

Skyway, a joint venture between BMD Constructions and CPB Contractors, was awarded the Airfield Works contract in July 2017.

The joint venture has achieved:

  • Airfield conduits and pits 90 per cent complete
  • Modified fine crushed rock (taxiway pavement base course) 80 per cent complete
  • Taxiway concrete (final taxiway pavement layer) more than 50 per cent complete

Following the completion of the construction programme, the detailed commissioning process for the new ground lighting, navigational aids and control tower systems will commence.

Brisbane’s new runway remains on track to be operational in mid-2020.

0 Comments

Leave a reply

Your email address will not be published. Required fields are marked *

*

CONTACT US

We're not around right now. But you can send us an email and we'll get back to you, asap.

Sending

©2019 Energymagazine. All rights reserved

Log in with your credentials

Forgot your details?