The Sydenham Station upgrade – part of Sydney Metro –  is progressing with five large roof canopies recently installed.

The canopies, each weighing more than 20 tonnes, are part of a new pedestrian concourse, and required more than 400 people working 24-7 over two weeks to deliver. 

The new pedestrian concourse will connect the two new plaza entrances to the station on Railway Parade and Burrows Avenue.

A 500 tonne crane installed roof canopies, which were built during a road closure on Burrows Avenue as they were too large to be transported by truck.

Other work at Sydenham included:

  • More than 3km of new overhead wiring installed as part of the remodelling of Sydenham Junction
  • 50km of new signal cabling installed
  • 6,000 tonnes of new track ballast was brought into the site

Platforms 1 and 2 have been closed so they can be upgraded to Sydney Metro platforms, including the installation of platform screen door technology.

Commuters on the T3 Bankstown Line will use platforms 3 and 4 at Sydenham until Sydney Metro opens in 2024.

0 Comments

Leave a reply

Your email address will not be published. Required fields are marked *

*

©2020 Energymagazine. All rights reserved

CONTACT US

We're not around right now. But you can send us an email and we'll get back to you, asap.

Sending

Log in with your credentials

Forgot your details?